Table 4
EDF method installation factors as a function of FOB equipment cost in carbon steel and associated piping installation sub-factor. Values are on a 2020 basis and sourced from [36].
Equipment cost | Installation factor |
Piping factor |
---|---|---|
CEq,CS (k€) | FT,CS | fpp,CS |
0–10 | 14.98 | 2.24 |
10–20 | 10.12 | 1.54 |
20–40 | 8.54 | 1.22 |
40–80 | 7.22 | 0.96 |
80–160 | 5.89 | 0.76 |
160–320 | 4.92 | 0.60 |
320–640 | 4.19 | 0.48 |
640–1280 | 3.63 | 0.38 |
1280–2560 | 3.19 | 0.30 |
2560–5120 | 2.84 | 0.23 |
5120– | 2.56 | 0.19 |