Table 8

Inspection and maintenance check.

Sr. No. Subsystem/Component Things to inspect Maintenance schedule Repair/Replace
1 Site The array is not shaded Monthly Repair
All debris from/around/under the array is removed. Repair
2 PV module and solar array (including mounting structure) All individual modules are cleaned Monthly/Annually Repair
No visual defects in the module Replace
No discoloration Replace
No indication of moisture penetration Repair
No indication of corrosion Repair
The array is firmly fixed. Repair
No loose or missing panel clamp Repair
3 Wiring system No mechanical damage to the cables 6 months Replace
Cable ties do not damage cables. Poor or mismatched connection. Replace
Connections are not frayed, loose, or corroded. Replace
Conduit ends are adequately sealed. Repair
Conduits and cables are firmly supported. Repair
4 Electrical characteristics Verify short circuit current Monthly Repair
5 Protective devices and isolators Fuses and holders are still intact Monthly Repair
MCB and RCD operate correctly Replace
The earthing system operates correctly. Repair/Replace
Isolators function correctly Repair
6 Labels and signs Green PV label in place During inspection Replace
The shutdown procedure is visible and readable. Replace
Disconnecting devices are adequately labeled. Replace

Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.

Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.

Initial download of the metrics may take a while.