Table 1
Risk classification of each risk index.
Risk level | Risk-free | Low risk | Medium risk | High risk |
---|---|---|---|---|
Bad behavior handling records | No record | General misbehavior | Gross misconduct | Particularly serious misconduct |
Delivery timeliness | Supplier on time delivery | Due to the supplier’s delayed delivery, no more than 1 project unit will be affected within 12 months | The supplier delayed delivery due to the cumulative impact on 2 project units within 12 months | Due to delayed delivery by the supplier, the cumulative impact on 3 or more project units within 12 months |
Service satisfaction | 100 points | [70, 100] | [50, 70] | Below 50 points |
Quality inspection before delivery | Sampling pass rate ≥90%; Reinspection and multiple owner unit testing are qualified | Random inspection pass rate (80–90%), but reinspection and multiple owner units test qualified | Random inspection pass rate (70–80%), but reinspection and multiple owners of the unit test qualified | The pass rate of sampling inspection is less than 70% or the reinspection fails or multiple owner units fail to pass the test |
Arrival acceptance | Up to standard | – | – | Below standard |
Handover test acceptance | Up to standard | – | – | Below standard |
Product operation | 100 | – | [40, 100) | [0, 40) |
Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.
Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.
Initial download of the metrics may take a while.